St Mary's University, Biochemistry Lab - Twickenham, Middx
This project involved the careful removal of the old laboratory and installation of a new state of the art facility.
Completed ahead of schedule during summer recess.
"This project was complicated by late initial instructions from the client on a time critical programme and also late delivery of client ordered furniture. ACS had to re-sequence their programme to ensure completion date was not compromised and work closely around client direct contractors which they more than adequately achieved."
Andrew Todman , MD , BOW Projects